untitled shoot-2688edited
A lot has happened since the last writing about the project. The foundation and floors were completed and the framing of the garage and shop and the house has begun.
All the plumbing and propane supply lines were in place and neatly organized.
untitled shoot-2415
The tubing for the closed hydronic floor heating system was installed during the pour of the floor. The tubes could have a tendency to float a little in the concrete before it sets and since cuts were made in the floor to control expansion and contraction, Matt wanted to ensure that the system was not compromised. He pressurized the tubing and tested it to confirm that it maintained pressure.
untitled shoot-2417
Footing drains were installed.
untitled shoot-2252
The foundations, septic system and water cistern were backfilled by Mike Ogle - Mogle Excavation.
untitled shoot-2430
Mike lives down the street from the project and is an avid skier. Thus the name of his business - Mogle Excavation.
untitled shoot-2278
There has been a lot of rain this Spring.
untitled shoot-2697edited
While the rain is welcome due to the forecast of a dry hot summer, the mud is sticky, slick and hard to work in.
untitled shoot-2516
We had to scramble to get the drain field for the septic system completed before a scheduled inspection, but we got it done with some time to spare. Even though it was difficult to work on in the mud, it looked neat and orderly in the end.
untitled shoot-2512
Ben is working on the framing.
untitled shoot-2708
Matt and Ben keep an eye on a thunder storm on the ridge.
untitled shoot-2704
The framing seems to be going very quickly, It is thrilling to see what were once ideas and drawings taking physical shape. This is just as I had envisioned.
untitled shoot-2707
The view from the future bath room. It is amazing to stand where the rooms are positioned and see the view framed by the windows.
untitled shoot-2698edited